The Role of Advance Payment Guarantees in Construction Projects in Bahrain
In construction projects, especially large-scale or high-risk ones, contractors often require advance payments to mobilize resources, procure materials, and initiate work. However, these payments carry risks for the project owner. To balance trust and security, contracts commonly include an Advance Payment Guarantee (APG) , a financial instrument that protects the employer’s money if the contractor fails to deliver.
In this article, we’ll explain what Advance Payment Guarantees are, how they work under Bahraini law, and how both parties can protect their interests legally. We’ll also share a general example to show how lawyers play a key role when disputes arise.
Learn more about our Construction Law services in Bahrain.
What Is an Advance Payment Guarantee?
An Advance Payment Guarantee is a written commitment, usually issued by a bank or insurance company, assuring the project owner (also called the employer or client) that the advance payment will be refunded if the contractor fails to fulfill their contractual obligations.
In essence, it gives the client financial security that the advance money won’t be lost while allowing the contractor to receive upfront funds without fear of non-payment.
How It Works
- The contractor requests advance payment to mobilize the project.
- The employer agrees, provided the contractor submits an Advance Payment Guarantee.
- A bank or insurer issues the guarantee in favor of the employer.
- If the contractor defaults, the employer can call the guarantee and recover the advance.
This process allows the project to move forward efficiently while reducing the employer’s financial risk.
Legal Considerations in Bahrain
Under Bahraini law and industry practice, Advance Payment Guarantees are enforceable independent financial guarantees. This means:
- They are separate from the main contract, and
- The employer can call the guarantee without proving breach, as long as the conditions are met.
However, to be legally valid and enforceable, the APG must be:
- Properly worded and signed by an approved financial institution
- Linked to a clear contract reference
- Time-bound, often expiring after a specific period or project milestone
- In a format acceptable under local banking regulations
FIDIC contracts and Bahraini public tenders almost always require APGs before releasing any advance payments.
Common Disputes Involving Advance Payment Guarantees
Despite their protective purpose, APGs can trigger disputes if not handled carefully. Typical issues include:
- The employer calling the guarantee prematurely
- The contractor disputing the validity of the call
- Ambiguities in the guarantee wording
- Expired or lapsed guarantees due to poor contract management
- Delays in refunding the advance after project termination
Example
In a government infrastructure project, a contractor received a 10% advance payment after submitting a bank-issued Advance Payment Guarantee. However, six weeks into the project, the contractor halted operations due to internal financial issues and failed to mobilize equipment as agreed.
The employer issued formal notices and, after no corrective action, proceeded to terminate the contract. A lawyer was consulted to assess whether the conditions to call the APG were met. Upon confirming the guarantee was still valid and the contractor was in clear breach, the employer filed a claim with the issuing bank.
After review, the bank released the guaranteed amount to the employer helping recover a large portion of the advance and minimizing the financial loss.
This example highlights the importance of well-drafted guarantees, timely legal action, and contractual awareness from both sides.
Our Construction Law Firm in Bahrain provides expert legal services.
Tips for Project Owners and Developers
- Always require a valid Advance Payment Guarantee before releasing any funds.
- Ensure the guarantee is issued by a licensed and reputable institution in Bahrain.
- Check that the wording is unconditional, allowing payment upon demand.
- Set clear expiration dates linked to project milestones or work completion.
- Maintain copies of all guarantee documents and monitor deadlines closely.
Tips for Contractors
- Understand the obligations tied to the APG failure to perform could lead to a claim.
- Ensure the guarantee is in the correct format and clearly linked to the contract.
- Maintain clear records of advance payment use and work progress.
- Replace or renew the guarantee if the project timeline is extended.
- Seek legal advice before agreeing to guarantee terms that may expose you to unnecessary risk.
In our previous blog on Can You Claim Damages for Project Delays in Bahrain Construction Contracts?