Liquidated Damages Explained: Legal Protection for Delayed Projects in Bahrain

Liquidated Damages Explained: Legal Protection for Delayed Construction Projects in Bahrain


Delays in construction projects are common, but when they result in financial losses or missed deadlines, the consequences can be severe. That’s why most construction contracts in Bahrain include a Liquidated Damages (LDs) clause a powerful legal tool that defines in advance the compensation payable for delays.

Liquidated damages provide certainty, reduce the burden of proving actual loss, and help both contractors and project owners manage risk effectively. In this article, we explain what liquidated damages are, how they work under Bahraini law, and how to handle disputes related to project delays.


Explore our expertise in Bahrain Construction Law.


What Are Liquidated Damages?

Liquidated damages are a pre-agreed financial penalty written into a construction contract. They specify the amount payable by the contractor to the project owner for each day or unit of delay beyond the agreed completion date.

For example, a contract may state that the contractor must pay BHD 500 per day if the project is not completed by the handover date. This provides clear consequences for delay without the need for the project owner to prove actual financial loss.

 

 Legal Status in Bahrain

Liquidated damages are recognized under Bahraini civil and commercial law and are enforceable provided that:

  • They are clearly stated in the contract
  • The delay is not excused (e.g. force majeure or valid extension of time)
  • The amount is reasonable and not punitive

If the amount is deemed excessive, a court or arbitral tribunal in Bahrain may reduce it but it will not reject the clause altogether unless it’s proven to be unfair or unlawful.

Standard construction contracts used in Bahrain, including FIDIC-based agreements, often contain detailed liquidated damages clauses for delay, non-performance, and milestone breaches.

 

 Why Use Liquidated Damages?

  • Avoids disputes over calculating actual damages
  • Saves time and legal costs by predefining liability
  • Encourages timely performance by contractors
  • Strengthens legal protection for developers and employers
  • Provides a predictable remedy in case of delay

 

 Common Mistakes and Risks

  • Not issuing formal notice of delay
  • Miscalculating the start date for delay penalties
  • Using vague or poorly drafted LD clauses
  • Failing to prove the contractor caused the delay
  • Applying LDs when the delay was outside the contractor’s control

To avoid these risks, it's critical to understand how the clause functions, follow proper procedures, and document all delay-related events.

 

Example

In a commercial office tower project, the contract specified a completion deadline of 18 months and included a liquidated damages clause of BHD 800 per day for delays. As the deadline passed, the contractor requested an extension citing weather-related disruptions. However, no formal extension was granted.

The delay extended for 35 days, during which the developer was unable to lease the property. A lawyer was engaged to assess whether liquidated damages could be applied. Upon reviewing site reports, correspondence, and contract clauses, the lawyer confirmed that the contractor failed to follow proper procedures for an extension of time.

A formal LD notice was issued, and the contractor was held liable for BHD 28,000, which was deducted from the final payment. The matter did not escalate further due to the clarity and enforceability of the contract clause.

This example demonstrates how well-drafted LD clauses and timely legal advice can resolve delay claims without prolonged dispute.


Work with experienced Construction Lawyers in Bahrain for project claims.


 Best Practices for Project Owners and Developers

  • Include a specific and measurable LD clause in every contract
  • Tie LDs to key milestones or handover dates
  • Ensure the amount is reasonable and proportionate
  • Keep detailed progress records and delay notices
  • Engage legal advice before issuing a claim

 

Best Practices for Contractors

  • Review LD clauses carefully before signing the contract
  • Monitor deadlines closely and request extensions of time in writing
  • Maintain records of any disruptions or delays outside your control
  • Communicate proactively with consultants or project owners
  • Get legal support if a claim is made against you unjustly


In our previous blog on The Role of Advance Payment Guarantees in Construction Projects in Bahrain


Share this post
Tags
manal dhahi

Manal Dhahi

Founder of Manal Dhahi Legal Consultants

Tel : +9731716 2211
info@manalfirm.com

Archive
The Role of Advance Payment Guarantees in Construction in Bahrain