Variation Orders: How to Legally Change the Scope of Work in Bahrain Construction Projects
In the world of construction, change is inevitable. Whether due to design modifications, site conditions, regulatory changes, or client needs, almost every project will require adjustments during its lifecycle. In legal and contractual terms, these changes are formalized through Variation Orders.
A Variation Order is not just a casual change it's a legally binding amendment to the contract that alters the original scope of work, and it must be handled with precision to avoid disputes, delays, or financial losses. In this blog, we explain what Variation Orders are, how they work under Bahraini construction law, and how both contractors and project owners can protect their interests through proper documentation and legal awareness.
Learn more about our Construction Law services in Bahrain.
What Is a Variation Order?
A Variation Order (also known as a “change order”) is an official instruction issued by the project owner (or consultant/engineer on their behalf) to change the scope of the contracted works. This may include:
- Adding or removing work
- Modifying specifications or materials
- Changing the sequence or timing of tasks
- Adjusting dimensions, finishes, or locations
Variation Orders are common in projects that involve civil, mechanical, or electrical works and must be agreed upon in writing by all relevant parties before being implemented. Failure to properly document and approve variations can lead to serious legal and financial consequences.
Legal Basis for Variation Orders in Bahrain
Under Bahraini construction contracts “especially those based on FIDIC standards” the right to issue Variation Orders is typically granted to the engineer or project owner. However, the law requires:
- Mutual agreement on pricing, timeline adjustments, and scope changes
- Written documentation before execution
- Proof of impact if disputes arise regarding delays or costs
If a Variation Order increases the cost or affects the project duration, the contractor has the right to request an adjustment to the contract value and/or the completion date — provided proper procedures are followed.
Why Legal Clarity Matters
When Variation Orders are not handled properly, they often become one of the leading causes of disputes in Bahraini construction projects. Common issues include:
- The employer denies the variation later, claiming it was never approved.
- The contractor proceeds without written approval and cannot claim extra costs.
- Disagreement on pricing or impact on the project timeline.
- Multiple undocumented changes leading to contractual confusion.
A clearly written contract, along with a well-maintained variation register, is essential to protect both parties from risk.
Example:
In a mid-scale commercial building project, the developer requested a change in the interior layout midway through execution, asking to convert part of the retail space into a medical facility. The contractor agreed verbally and began implementing the changes, which required plumbing, HVAC, and electrical modifications.
Later, when the contractor submitted a claim for the additional work, the developer refused, stating that no written Variation Order had been issued. A legal advisor reviewed the case and found that although emails had discussed the change, no formal document had been signed by both parties.
The dispute was ultimately resolved through mediation, but the contractor suffered delays and unrecoverable costs a situation that could have been avoided with proper documentation and legal review prior to executing the change.
Our Construction Law Firm in Bahrain provides expert legal services.
Best Practices for Project Owners and Developers
If you are a developer or project owner, always:
- Issue Variation Orders in writing before any work begins.
- Include a detailed description of the change, pricing, and any time extension.
- Ensure both the contractor and engineer acknowledge and sign the variation.
- Keep a variation log and update the contract records.
Best Practices for Contractors
For contractors, protecting your legal and financial interests means:
- Never begin variation work without written approval.
- Submit a Variation Request clearly stating the change, cost impact, and time extension (if any).
- Keep documentation and correspondence related to the change.
- Seek legal advice before proceeding with disputed or unclear changes.
How Legal Support Helps
A construction lawyer can:
- Draft Variation Order templates tailored to Bahraini law and your project
- Review your contract to ensure variation procedures are legally enforceable
- Advise on how to manage undocumented changes already performed
- Represent your interests if a dispute arises regarding variation claims
Legal advice is especially important in high-risk or high-value projects, where a single variation can significantly impact budget, delivery, or liability.
In our previous blog on Retention Money in Construction Projects: Legal Rights & Risks in Bahrain